This guide sets out the electric screw press maintenance routine AYANK recommends for the J58KA and J58ZKA series, from 250T to 10000T: what to check before the first test run, the operating limits that prevent overload, the mechanical tolerances worth measuring every month, and the electrical and sensor checks that catch failures before they stop the line. It applies to the whole forging screw press range. Good upkeep keeps forging accuracy, extends service life and protects output.
Thin oil lubrication station. Before the equipment is tested, fill the thin oil lubrication station with 68# guide rail lubricating oil and run the station. Replace with new oil after a week and check the oil tank level frequently to ensure normal lubrication of the equipment.
Grease lubrication pump. Before commissioning, fill the grease lubrication pump with 00# lithium-based grease (00# in spring, summer and autumn, 000# in winter). Turn on the lubrication pump to make sure the screw pair and guide rail are fully lubricated, then switch to automatic lubrication.
Flywheel oil cups. There are two pressure-injection oil cups above the flywheel for lubricating the flywheel copper sleeve. Inject an appropriate amount of 00# lithium-based grease every quarter.
To keep the electric screw press in good working condition for a long time, the following operating procedures must be strictly followed.
(1) Set energy on small-deformation work. When imprinting, correcting, or forging hardware tools, tableware and medical equipment — work with small deformation, large deformation force and rigid impact — the set energy must not exceed 40% of the nominal energy, to avoid overloading and equipment failure. Pay particular attention when forging low-deformation parts such as valves and tableware, and during stamping and correction.
(2) Minimum die height. Whether the press is running or idle, the distance between the bottom surface of the slider and the flat surface of the workbench pad must not be less than 560 mm. In other words, the die height including the die base must not be lower than this value.
(3) Air line. The air pressure and safety valve of the air pipeline must be adjusted to the specified pressure, and there must be no air leakage at any connection.
(4) Overload safety device. Adjust it accurately, safely and reliably: the tightening bolt preload is set so that the flywheel friction safety device slips slightly when the machine's impact force reaches 10,000 kN.
(5) Lubrication points. Ensure every lubrication point has enough lubricating oil. The oil must be clean and every lubrication point should be confirmed flowing before start-up.
(6) Guide rail gap. If the guide rail is worn, the insert screws are loose, or during overhaul, adjust the guide rail gap to preserve the accuracy of the press.
(7) 10,000-cycle fastener check. After every 10,000 operating cycles, inspect all connecting parts of the machine and tighten any loose bolts.
Mechanical maintenance covers four groups of parts. Measure each clearance below and log the reading and the date, so that a trend rather than a single measurement tells you when a part is due for replacement.
Check the foundation pit for contamination, standing water and accumulated oxide scale, and clean it if necessary. Check whether the worktable is deformed; if it is, contact our after-sales team for repair in time. Check whether the anchor bolts and wedge irons are loose, and adjust the preload manually if they are. Check whether the foot switch is oxidised or blocked by foreign matter, and clean it in time. Keep the working space around the dies and above the slider clean and free of foreign matter at all times. Check that the guide plate screws are tight, and tighten immediately if any are loose.
Check the axial clearance between the thrust bearing and the screw — the limit is 0.7 mm or less, and it should be adjusted once it grows beyond that. Check the guide rail gap; the comprehensive clearance is 0.4–0.6 mm, and it should be adjusted once it increases. Check the guide rail contact surface for wear and scratches, and contact our after-sales service department in time. Check that the flywheel bolts are not loose, and adjust the preload if they are. Check whether the pinion gear compression nut is loose; if so, adjust the preload or replace the disc spring. Check the backlash between the large and small gears — the tooth clearance is 0.5–0.7 mm. Check the pinion gear for damage or carbonisation, and replace it if either is found.
If one of these clearances cannot be brought back into range by adjustment, the mating part usually needs replacing. Contact AYANK with your J58ZKA electric screw press model and serial number before ordering.
Check whether the brake screw is loose, and tighten it if so. Check the brake spring for deformation or damage, and replace it if either is found. Check the brake friction plate for wear — the gap is 2–3 mm; once it exceeds this, adjust or replace the plate.
Check the ejector oil pipe for damage, and make sure the joints are not loose. Check the lubrication system and lubricating hydraulic station for sufficient oil, and for leaks at joints and pipes. Check the working status of the hydraulic lubrication pipeline for damage or leakage. Check that there is enough oil in the oil tank, oil pool, oil cup and pump, and clean them in time if there is dirt. Check every oil injection point, pipe and joint for oil leakage, and replace the seal immediately if any is found.
Electrical maintenance here is mostly visual and functional: dust, heat, loose terminals and alarms. None of it needs the cabinet opened under power.
Check the main power supply; the rated voltage should stay within ±10%. Check that the emergency stop button works and can stop the machine normally. Check that the inverter is clean and free of dust. Check the control panel indicator lights and make sure they switch on and off normally. Check the buzzer in the control box and make sure it sounds and stops normally. Check the alarm light on the control box and make sure it illuminates, sounds, stops and goes out normally.
Check the motor connecting parts for looseness or deformation, and adjust the preload or replace them in time. Check the main motor terminals and make sure they are undamaged with normal preload. Check the wiring screws on the thermal relay and make sure all are tight. Check the electrical components in the cabinet for damage. Check the terminal screws on all electrical components and on the motor junction box, and make sure every screw stays tightened.
Check the appearance of the pneumatic system and make sure the connecting wires are intact and unbroken. Check the electrical pipelines for damage or leakage. Check the joints and replace any seal that has failed. Check the air filter for looseness, damage and blockage.
Check the encoder transmission mechanism and the belt for ageing and cracking, and replace in time. Check the pressure display and make sure working pressure stays within range. Check the liquid level sensor, the blockage sensor, the total air source pressure sensor and the thin oil flow sensor for normal status and for alarms.
Carry out daily, weekly, monthly and quarterly inspections strictly according to the inspection locations and standards in the inspection schedule, and perform the corresponding maintenance as required to keep the overall performance and safety of the screw press.
| Interval | Action |
|---|---|
| Before first run | 68# guide rail oil in the thin oil station; 00# lithium grease in the lubrication pump; confirm every lubrication point is flowing |
| One week after first run | Replace the thin oil with new oil; check the oil tank level |
| Quarterly | Inject 00# lithium-based grease into the two flywheel oil cups |
| Every 10,000 cycles | Inspect all connecting parts and tighten any loose bolts |
| Daily / weekly / monthly / quarterly | Mechanical and electrical checks listed in sections 3 and 4 |
If a reading falls outside the tolerances above and cannot be corrected by adjustment, contact AYANK with your model and serial number before the next production run. The J58KA electric screw press page lists the tonnages and applications this routine covers.